Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Firefighters extinguish early-morning blaze in Rossland

Neighbour alerted family of four, no injuries reported

Rescued snowmobilers ill-prepared for emergency, Castlegar RCMP say

Two men rescued Wednesday night were not ready for overnight in back country

Senior curling provincials setting up for exciting finish

Standings tight as Senior curling teams push for provincial playoffs

Police share more details on occupants and suspicious van in Fruitvale

Vehicle in question offered young girl a ride to school on Feb. 19

Fashion Fridays: Must have wardrobe basics

Kim XO, helps to keep you looking good on Fashion Fridays on the Black Press Media Network

National Energy Board approves Trans Mountain pipeline again

Next step includes cabinet voting on the controversial expansion

Skier dies at Revelstoke Mountain Resort

Cause of death for young man has not been released

R. Kelly charged with 10 counts of sexual abuse

R&B star has been accused of sexual misconduct involving women and underage girls for years

More sailings coming to 10 BC Ferries’ routes

Transportation Minister Claire Trevena said the sailings were originally cut in 2014

B.C. police watchdog clears officers in fatal hostage situation outside Cranbrook

A woman died from carbon monoxide poisoning after taking two minors hostage last fall

Cryptocurrency exchange CEO who suddenly died leaves Kelowna house in will

Gerald Cotten, holding the keys to money tied up in his virtual currency exchange, died in December.

Regulator’s report, coming today, unlikely to settle Trans Mountain pipeline battle

The Trans Mountain pipeline will remain a controversial topic both in the political ring and out

Most Read