Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

RCMP renew request for help finding missing Nakusp man

Christopher Sanford was reported missing Aug. 5

Updated: Early-morning fire near Trail destroys travel trailer and van

An arson-trained RCMP investigator will examine the scene

Anglican churches in Nelson, Balfour, Kaslo to marry same-gender couples

Rev. Jeff Donnelly says he’d love to host LGBTQ weddings

Update: Two women injured after motorcycle accident in Trail

The collision occurred Wednesday night just after 9 p.m.

Pregnant Kootenay teachers fight to change compensation rules

Risk to unborn babies not recognized by WorkSafeBC

QUIZ: How much do you remember about Woodstock?

Weekend music festival in Bethel, New York, was held 50 years ago

Advocates ‘internationalize’ the fight to free Raif Badawi from Saudi prison

Raif Badawi was arrested on June 17, 2012, and was later sentenced to 1,000 lashes and 10 years in jail for his online criticism of Saudi clerics

RCMP, search crews hunt for 4-year-old boy missing near Mackenzie

George went missing early Saturday afternoon

Canadian entrepreneurs turning beer byproduct into bread, cookies and profits

Some breweries turn to entrepreneurs looking to turn spent grain into treats for people and their pets

Canada ‘disappointed’ terror suspect’s British citizenship revoked

Jack Letts, who was dubbed “Jihadi Jack” by the U.K. media, has been detained in a Kurdish prison for about two years

Chrystia Freeland condemns violence in Hong Kong, backs right to peaceful assembly

There have been months of protests in the semi-autonomous region

B.C. VIEWS: Log exports and my other errors so far in 2019

Plastic bags, legislature overspending turn out differently

Most Read